A UK repairs contractor in an empty, cleared council flat checking a job sheet on a clipboard beside a step ladder and dust sheets
Pricing & Bidding

Inside Social Housing Repairs Contracts: Voids, Day Rates and Schedule of Rates Pricing

Mo El Hadri
Stories by Mo El Hadri
@mointhemarket·14 November 2026·11 min read

Social housing repairs contracts are long-term agreements where a housing association or council pays a contractor to fix, empty-turn and maintain its homes at prices fixed in advance, usually against a schedule of rates. If you want steady work from that world, the first thing to understand is that nobody is going to ask you for a quote. The price exists before the job does.

That changes how you make money. On private work you win on the quote. Here you win on knowing which jobs pay at the rates on offer, which do not, and how to claim properly for what you found on site. This post walks through how the contracts are built, why voids are the usual way in, and the specific places the margin lives, using real item rates from the NHF Schedule of Rates V7.2 data we hold.

The three kinds of work inside a repairs contract

A landlord with thousands of homes does not buy repairs one at a time. It lets the work in blocks, typically for several years, and most contracts split into the same three streams.

Responsive repairsVoidsPlanned works
What it isTenant reports a fault, you attendEmpty home made ready for the next tenantProgrammes: kitchens, bathrooms, roofs, decoration
Job sizeSmall, often under £100Hundreds to a few thousand poundsLarge, repeated across many homes
AccessTenant has to be inEmpty, keys from the landlordBooked with tenants in advance
What the landlord measuresResponse time, first-time fixDays to hand the home backProgramme and quality

Responsive repairs is the stream with the legal clock on it. Since 27 October 2025, Awaab's Law has required social landlords in England to make emergency hazards safe within 24 hours, to investigate a potential significant damp and mould hazard within 10 working days, and to complete the safety work within 5 working days of that investigation finishing. The landlord carries the duty, but it passes the timescales straight into the contract. If you take responsive work, you are taking those deadlines.

How the pricing works: one percentage on thousands of rates

Most social housing repairs are priced on the NHF Schedule of Rates, published by M3 Housing for the National Housing Maintenance Forum. It is a library of coded tasks, each with a written description, a unit and a base rate. The V7.2 data we hold has 3,440 of them.

The contractor bidding for the contract does not price those items one by one. It bids a single percentage above or below the base rates, and every order for the life of the contract is paid at base rate adjusted by that figure. One published contract on the newer version 8 schedule fixed it at plus 12 percent for responsive repairs and plus 10 percent for voids. That is one landlord's contract, not a market norm, and there is no published average.

If you are a subcontractor, you will normally be offered the same schedule at a discount, something like "SoR minus 10". That gap is the contract holder's margin for managing the landlord, the orders and the paperwork. Your job is to work out whether the items you will actually be given still pay at that discount.

Why voids are the way in

A void is a home that is empty between tenants. England recorded 263,000 new social housing lettings in 2024/25, and for existing homes the median time a property sat vacant before being relet was 30 days. Every one of those days is rent the landlord does not collect, so void turnaround is one of the numbers a housing director gets asked about.

For a small firm, voids have three things going for them:

  • No access problem. Nobody has to be in. You collect keys and work a full day. On responsive repairs, a tenant who is out when you arrive can wipe out the margin on the whole visit.
  • Several items in one visit. A void is a list: clear, clean, locks, safety checks, repairs, decoration. One trip, many paid lines.
  • The contract holder needs capacity. Voids arrive in lumps. When ten homes come back in one week, the company holding the contract needs extra hands fast, and that is when a new sub gets a trial.

The schedule itself shows how much of it is built around empty homes. In the V7.2 data, 278 items carry the X priority code instead of an emergency, urgent or routine one, and 201 of those sit in just two trades: painting and decorating, and cleaning and clearance. Another 11 items are named for voids outright, covering things like draining down the water, capping the gas and the landlord's gas safety check.

A worked void, priced from the schedule

Here is a plausible order for a one-bedroom flat handed back in ordinary condition, priced at V7.2 base rates before any percentage.

ItemCodeBase rate
Clear out dwelling complete460003£79.41
Clean to lettable standard460012£99.26
Full lock change, front door390929£98.22
Landlord's gas safety check and report730009£63.68
Electrical test and certificate, unoccupied property896001£137.99
Water safety check and report690005£28.72
Wash down and redecorate room up to 20 sq m, x3450507£503.40
Clear garden debris460025£49.54
<strong>Base total</strong><strong>£1,060.22</strong>

At plus 10 percent, the contract holder is paid £1,166.24 for that void. If it passes the whole list to a subcontractor at the schedule minus 10 percent, the sub is paid £954.20 and the contract holder keeps £212.04, about 18 percent of what it was paid. Those two percentages are an illustration, not figures from a particular contract. The structure is the point: the same price list runs down the whole chain, with a slice taken at each level.

Now ask the only question that matters. Can you clear, clean, change the locks, run three safety checks, decorate three rooms and clear the garden for less than £954 in labour, materials, tipping and fuel? If you carry the gas and electrical tickets in-house, probably. If you have to buy in both certificates, the test items alone may cost you more than they pay.

Where the margin actually lives

The rate is fixed, so you cannot price your way to a profit. These are the levers you do have.

1. Code the job you found, not the job on the order

The order is raised by someone who may never have opened the front door. The schedule has three different clearance items for the inside of a home, and the gap between them is large:

Clearance itemCodeBase rate
Clear out dwelling complete460003£79.41
Clear exceptionally dirty dwelling460009£281.00
Clear socially and environmentally dirty dwelling460010£569.63

Same address, same visit, and the top item pays more than seven times the bottom one. If you turn up to a home that is plainly in the third category and do the work on the first code, you have given away about £490 before lunch. Photograph everything before you touch it, send the photos to the landlord's representative, and get the order changed to the item that matches. This is not gaming the contract. It is what the three codes are there for.

2. Get extras instructed before you do them

Read the descriptions. The standard clear-out item says a skip, where one is needed, is charged separately. The skip item (£271.20) says it is only to be charged when specifically instructed. So the order of events decides whether you get paid: instruction first, skip second. The same goes for stripping wallpaper before decorating, which is its own extra at £128.61 for a room up to 20 square metres. Do it without an instruction and you have done it for free.

3. Measure, because the bands are steep

Decoration is paid by room, banded on ceiling area. A full redecoration of a room up to 20 square metres is £258.24 at base rate. The next band, 20 to 25 square metres, is £328.14. A large living room coded as a small one costs you £69.90 every time. Carry a laser measure and put the figure on the job sheet.

4. Do not plan around day rates

Plenty of trades walk into this work assuming that anything awkward will be paid on a day rate. The schedule says otherwise. Of 3,440 items in the V7.2 data, 4 are priced by the hour: jetting a blocked drain (£90), two roof survey items (£100) and an extra for additional labour in a confined space (£30.04). There is no general hourly rate for a joiner or a plumber in the book.

Where a job has no matching item, the contract sets what happens: a quotation, a rate built up from labour and materials, or dayworks at a rate written into the contract. All three normally need agreeing before the work starts. Ask the contract holder, on day one, what the dayworks rate is and who can authorise it. If the answer is vague, assume you will not be paid on it.

5. Watch the small emergency items

Responsive repairs is full of items like this one: locate an electrical fault, test and reset, £25.30 at base rate, an emergency-coded item whose own description says it is the only item to be claimed for that visit. One of those is a loss. Twelve in a day on one estate can work. The economics of responsive work are route density and first-time fix, which is why a subcontractor covering a wide area usually does better starting on voids. If you are pricing your own time, work out your real labour cost first, including the driving.

How small firms actually get this work

Very few small contractors sign with a landlord directly. The repairs contract goes to a larger company with the insurance, accreditations and systems the tender demands, and that company subcontracts trades and whole voids. So the door you are looking for usually belongs to the contract holder, not the housing association.

  1. 01Find out who holds the contract. Awards are public. Our guide to reading contract award notices shows how to see which contractor just won a landlord's repairs work and when it starts.
  2. 02Register with them. The big repairs contractors run supplier registration, covered in how main contractor supply chain registers work.
  3. 03Offer one package you can price. "Void cleans and clearances in these postcodes" or "void decoration, three-day turnaround" is easier to say yes to than "general building".
  4. 04Ask for the rate card and the top items. Then cost them. If you are new to working under someone else's contract, start with how to become a subcontractor in the UK.

If you would rather go to landlords directly, through their approved lists and frameworks, PlanaJob has a step-by-step guide to getting work with housing associations. PlanaJob is built by the same team as Contractor Club. The directory behind it tracks 557 UK work sources, including 69 social landlords and housing procurement groups and 17 tier-1 contractors that hold large repairs and maintenance contracts.

Getting paid

Two things decide when the money arrives. The first is paperwork: on a schedule of rates you are paid on completed, evidenced orders, so photos before and after, the certificate attached, and the right codes on the job sheet. An order that bounces for a missing gas certificate does not get paid until it is fixed.

The second is the terms. Where the landlord is a public body covered by the Procurement Act 2023, a 30-day payment term is implied into sub-contracts under that public contract. Councils are covered and many housing associations are too, but not every contract is, so ask the contract holder which rules the head contract sits under and get your own terms in writing. For how to set what you pay people under you, see how much to pay subcontractors in the UK.

Is it worth it?

Social housing repairs will not make you rich on any single job. The rates are tight and the paperwork is real. What it gives you is volume that does not depend on your marketing: homes become empty every week whatever the economy is doing. Operators who do well at it treat it as a system. They know their cost on their 20 most common items, they code accurately, they get extras instructed, and they turn voids round faster than the next firm.

A note on the numbers: item counts and rates are computed from the NHF Schedule of Rates V7.2 data we hold and are base rates before any tendered percentage. Version 8 and each landlord's own indexed rates will differ, so check against the schedule in your contract. Lettings figures are from the government's social housing lettings statistics for England, 2024/25. Awaab's Law timescales are from the government's guidance for social landlords. Last checked 14 November 2026.

Contractor Club is where operators compare what repairs contractors are really paying, which packages are worth taking and how to price them. Request entry if you want the inside track.

Request entry to Contractor Club⟶
ShareXWhatsAppLinkedIn

Frequently asked questions

How do social housing repairs contracts work?+

A housing association or council lets its repairs to one or a few contractors for several years, usually split into responsive repairs, void refurbishment and planned works. Most of the work is not quoted job by job. It is ordered against a schedule of rates, a price list fixed at tender, and paid at the listed rate plus or minus the percentage the contractor bid. The contract holder then subcontracts much of the delivery to smaller firms on the same price list.

What is voids work?+

A void is a rented home that is empty between tenants. Voids work is everything needed to get it back to the landlord's lettable standard: clearing and cleaning, changing the locks, gas, electrical and water safety checks, repairs, and often redecoration. In England the median time an existing social home sat vacant before being relet was 30 days in 2024/25, and every one of those days is lost rent, so landlords care about turnaround as much as price.

Are social housing repairs paid on day rates?+

Mostly not. The standard price list in the sector, the NHF Schedule of Rates, prices work per item, per number or per metre. In the V7.2 data we hold, only 4 of 3,440 items are priced by the hour. A day rate only applies where the contract sets one for work that has no matching item, and the landlord's representative usually has to agree it before you start.

Can a small contractor get voids work?+

Yes, and voids are the most common first package. The property is empty, so there are no access problems, several trades can be done in one visit, and the contract holder is under pressure to hand homes back quickly. Most small firms get in as a subcontractor to the company that holds the repairs contract, not by tendering to the landlord directly.

Where is the margin on a schedule of rates contract?+

In four places: the percentage you agree against the base rates, coding each job to the item that matches what you actually found, getting extras instructed before you do them, and keeping travel and return visits down. The rate for a job is fixed, so profit comes from your cost per item and from claiming the right item, not from the price you can talk a client into.

The human behind The Playbook

Go deeper

Learn the model, then get in the room

The full breakdown of construction arbitrage lives on our sister site, constructionarbitrage.com. When you want the operators who actually run it, join the Construction Arbitrage Players community.

My listening book THE EDGE is out now - 24 chapters on how the money really moves through a contracting business, made to be listened to on the drive. Free to start. See what is inside.

My book The Family Secret - how construction arbitrage really works - is coming soon.

Only Players Know

The game is real. The room is closed.

Contractor Club is a private, application-only circle of construction arbitrage operators. If you think you belong inside, apply and the circle will decide.

More from the Playbook

View all ⟶